See how long your build will take, week by week
Example figuresSet your project and watch the programme change. We programme and price your job properly after a visit.
Your programme
- Design and drawings: weeks 0 to 6.
- Planning decision: weeks 6 to 16.
- I. Set-up and groundworks: weeks 16 to 20.
- II. Foundations and floor slab: weeks 19 to 23.
- III. Walls to first floor: weeks 22 to 27.
- IV. Upper floor and walls to eaves: weeks 26 to 31.
- V. Roof structure and covering: weeks 30 to 35.
- VI. Windows and doors in: weeks 34 to 37.
- VII. First fix, plaster, second fix: weeks 36 to 48.
- VIII. Finishes and handover: weeks 47 to 52.
Before work starts
16 weeks
Drawings, planning
On site
36 weeks
From March 2027
Expected finish
Nov 2027
52 weeks in all
Example budget Example figures
£390,000 to £540,000
Building work only, at example London rates
These are example figures, not a quote. Centurion will price your project properly after a visit.
Send this plan with your enquiryWhat can move the dates
These are the usual reasons a building job finishes later than planned. Allow for each one before work starts and the delays stay small.
-
If your job needs planning permission, nothing starts on site until the council decides. They have eight weeks for most householder applications, and new homes can take longer. If they ask for changes, add more time.
-
Building on or near a wall you share with a neighbour means serving them notice first, two months ahead for work on the wall itself. If they do not agree, surveyors draw up an award before that work can go ahead.
-
Your building inspector checks the work at set stages: the foundation trench before the concrete goes in, the drains before they are covered, and the finished job. Each visit has to be booked ahead, or the next trade waits.
-
Heavy rain floods trenches, frost stops concrete and mortar, and high wind stops work on a roof. Groundworks and roofing are the stages that feel the weather most.
-
Steels are made to the engineer's drawings, and windows, roof lanterns and kitchens are made to measure. Each one is ordered weeks ahead so it arrives when the walls are ready for it.
-
Moving a wall, adding a window or changing the kitchen once work has started means new drawings, new orders and sometimes a new approval. Settle the details before we start and your dates stay put.