Do I need a party wall notice?

Pick the work you're planning and when you'd like to start. You'll see which notices the Party Wall etc. Act 1996 asks for, how much warning next door gets and the last day to serve them.

What are you planning? Pick all that apply
We work back from this date.
Which notice your work usually needs
Work you're planningNoticeMinimum notice
Loft conversionParty structure notice (section 2)2 months
Rear or side extensionAdjacent excavation (section 6) if footings are within 3 m of next door's building, or within 6 m and below a 45 degree line from its foundations1 month
BasementAdjacent excavation (section 6), and often a party structure notice1 or 2 months
Removing a chimney breastParty structure notice (section 2)2 months
Steel beams into a shared wallParty structure notice (section 2)2 months
New wall on the boundaryLine of junction notice (section 1)1 month
Damp-proofing a shared wallParty structure notice (section 2). Repointing alone may not need one2 months
Inside changes onlyUsually no noticeNone

General guidance from the Party Wall etc. Act 1996, not legal advice. Every job is different, so ask a surveyor to confirm before you serve a notice.

Section drawing of your house and next door sharing a party wall, showing the work you have picked

Worked example: a loft conversion starting on Monday 22 March 2027.

Notices you need

  • Party structure notice

    Needed

    Section 2 at least 2 months

    Loft conversion: steels set into the party wall.

Serve your notices by

Friday 22 January 2027

8 weeks from today

Nothing to serve. If your plans change, check again.

Next door then has 14 days to reply.

Ask us to serve your notices

The three notices in the Act

Each notice covers different work and gives next door a different amount of warning. Whichever you serve, they have 14 days to reply.

  • Party structure notice

    Section 22 months

    For work to a wall you share with next door: cutting in steels, taking out a chimney breast, underpinning, raising, rebuilding or damp-proofing it.

  • Line of junction notice

    Section 11 month

    For a new wall on the boundary where there isn't one now. You need it whether the wall sits astride the line or wholly on your land.

  • Notice of adjacent excavation

    Section 61 month

    For digging within 3 metres of next door's building and deeper than its foundations, or within 6 metres and below a 45 degree line drawn down from them.

Surveyor's desk with elevation drawings, tape measures, a laser measure and a crack width gauge
A notice of adjacent excavation must come with plans and sections showing the work.

What happens after you serve notice

If next door agrees in writing, you can start once the notice period has run. If they don't, surveyors settle it with an award first.

  1. 1

    Notice served

    We serve it on every owner of next door, leaseholders included.

  2. 2

    Next door replies within 14 days

    They agree in writing or dissent. Silence counts as a dispute.

    AgreeDissentNo reply

  3. 3

    Surveyors appointed

    In a dispute, you share one agreed surveyor or appoint one each.

  4. 4

    Next door is recorded

    A schedule of condition records their side before work starts.

  5. 5

    The award is served

    It sets out what you can build, how and when, and who pays for what.

Let us serve your notices

Tell us what you're planning, the address and when you'd like to start. We'll confirm which notices you need, draw them up and serve them on next door, then deal with the replies.

  • Building or extending? We serve your notices and agree the award.
  • Had a notice from next door? We act for neighbours too. Party wall matters
  • Working across London and Essex.

We need your name and a phone number or email so we can reply. See our privacy notice.